Welbourne Park
Project Value: £5M
Sector: Residential (131 New homes)
Status: Complete: End of Q1 2024
A vital new Health Centre supporting Tottenham Hale’s growth as London’s
next affordable neighbourhood of choice.
Mechanical, electrical, public health services, insulation, fire protection, lightning protection, water treatment, ventilation and smoke & climate control.

Cortland Cassiobury
Project Value: £3.5M
Sector: Residential (studio, one, two & three bed apartments.)
Status: Complete: Start of Q2 2024
Amenities: Media Suite, club & business lounge, dog park & fitness centre
Mechanical, electrical, public health services, fire alarm, access control, wet & dry risers, BMS and smoke ventilation.

Sutton Park House
Project Value: £2.5M
Sector: Residential & Commercial
Status: Completed: Q1 2025
Mechanical, Public Health Services, Ventilation and Water treatment.

Potton Middle School
Project Value: £200,000
Sector: Education
Status: Complete: Q3 2023
Scope of works: Mechanical, electrical, BMS & security and public health.
St Andrews East & West School
Project Value: £400,000
Sector: Education
Status: Complete: Start of Q4 2024
Scope of works: Mechanical, electrical and public health
Caldecote Lower School
Project Value: £350,000
Sector: Education
Status: Complete: Start of Q4 2024
Scope of works: Mechanical, electrical and public health.
Wembley Link
Developer: Hub
Main Contractor: Henry Construction
Status: Due for completion Quarter 2 2023
This project consists of 256 residential units K&T are completing the full electrical systems package inclusive of specialist packages fire alarm, access control, TV IRS system, intruder alarm together with life safety integration of the smoke ventilation systems and generator back up.

Park Modern
Developer: Fenton Whelan
Main Contractor: Ant Yapi
Status: Due for completion Quarter 1 2023
The 190,000 sq ft south-facing will contain spectacular lateral apartments, three trophy penthouses and mews houses with prices from £2m to £60m.
The apartments span across nine floors, offering generous ceiling heights and floor-to-ceiling glazing opening onto private terraces, giving residents a front row view of the park and city skyline.
Three penthouses on the 8th and 9th floors provide 16,500 square feet of living space and 5,600 sqft of private wrap around terraces.
Priced at £60 million, the 9th floor penthouse offers over 7,000 square feet of lateral living space completely surrounded by over 2,400 square feet of terracing. Penthouse views include Kensington Palace, Royal Albert Hall, the Shard and the City of London skylines.

Bridport Place
Developer: Metropolitan Thames Valley & Hayward’s Heath Investments
Main Contractor: Henry Construction
Status: Complete
This project was a block of mixed tenure apartments consisting of private sale, social housing and shared ownership homes. K&T provided Full MEP package across this project.

Vandon House Hotel
Developer: Shiva Hotel Group
Main Contractor: Henry Construction
Status: Complete Spring 2020
This project in vibrant Westminster is a newly constructed 58-bedroom Hotel with five luxury flats with their own independent entrance. K&T delivered the full mechanical, electrical and public health packages together with the critical life safety systems.

Hat & Feathers Hotel
Developer: Omenport Developments
Main Contractor: Henry Construction
Status: Ongoing due for completion Quarter 4 2022
This project, in the heart of Barbican, surrounds and integrates the existing Landmark Hat & Feathers pub into a 143 bedroom hotel. K&T provided the complete Mechanical Electrical and public health packages together with the specialist packages basement smoke control, commercial sprinkler systems, BMS system Fire alarm and access control systems.